Thursday, 17 May 2018 06:15

No respite in Ramazan, Karachiites to face loadshedding a few more days

Written by TheIndianSubcontinent News Agency
Rate this item
(0 votes)
No respite in Ramazan, Karachiites to face loadshedding a few more days
No respite in Ramazan, Karachiites to face loadshedding a few more days

KARACHI: Karachiites would have to suffer a few more days in Ramazan as the K-Electric has still not completed the repair of Bin Qasim Power plant which developed a fault last month.

According to a company statement, KE's 180 megawatts Bin Qasim...

No respite in Ramazan, Karachiites to face loadshedding a few more days
No respite in Ramazan, Karachiites to face loadshedding a few more days

KARACHI: Karachiites would have to suffer a few more days in Ramazan as the K-Electric has still not completed the repair of Bin Qasim Power plant which developed a fault last month.

According to a company statement, KE's 180 megawatts Bin Qasim power station is expected to be re-energised till May 20.

The spokesperson said technical teams of KE and General Electric (GE) have begun installation of the ‘rotor’, imported from Holland at a cost of $5 million”.

“The rotor was airlifted from Holland through a Russian cargo plane and it reached Karachi on Wednesday morning,” KE spokesperson added. “The 41-ton equipment has reached the site and installation works are underway.”

The plant is fixed with a GE turbine, and GE’s technical team is assisting the power utility in restoring the plant’s operation.

On delay in the rotor shipment, KE spokesperson said the company needed the equipment matching the specifications and “for that purpose a sub-component has to be moved from Houston to Holland”.

“It’s a huge size equipment and cannot be kept in store, which is why it took some time in getting the rotor to the plant site,” the spokesperson added.

The process of installation and re-energising of the affected unit is expected to be completed in a few days, which would improve the power situation in the city.

In April, Prime Minister Shahid Khaqan Abbasi stepped in to resolve the tussle between KE and Sui South Gas Company (SSGC), leading to an increase in gas supply to power utility to 130 million metric cubic feet/day (mmcfd) from 90 mmcfd. The recent technical fault offset the benefits of increase in gas supply and to meet consumer demands of 2,700 megawatts.

Read 89 times Last modified on Thursday, 17 May 2018 06:14